I am trying to Test from one to another in 12.5 0- the scripts do copy but not all of the information in the columns is copying over from the original .
Original project has the following columns:
Step Name/Application/User ID/Description/EXPECTED Result/Actual Result.

But when I copy the script to the new project – information is being copied into the wrong columns – Application was copied into Actual Results and User ID was nowhere – driving me a bit crazy! I don’t have time to go in and re-input the missing or incorrectly labeled data.

I have attached images for reference.
enter image description here



Source link https://sqa.stackexchange.com/questions/34990/-alm-12-5-copy-scripts-between-project-